description: "A central feeding system RFQ needs a numbered source-to-receiver map, drawings, and a demand table, or three suppliers will quote three different machines."
---

[Home](https://kyshinmachinery.com/) / [Guides](https://kyshinmachinery.com/guides) / Material Handling System RFQ Checklist: Sources, Receivers, Distance and Throughput

RFQ checklist Published: September 14, 2026

# Material Handling System RFQ Checklist: Sources, Receivers, Distance and Throughput

Prepare a comparable material handling RFQ with numbered sources and receivers, routing, demand, resin condition, controls, utilities, and acceptance criteria.

![Material Handling System RFQ Checklist: Sources, Receivers, Distance and Throughput guide cover](https://kyshinmachinery.com/images/guides/four-week-2026-09/material-handling-system-rfq-checklist.webp)

A "central feeding system" quote from three suppliers will come back as three different machines. One prices a blower, a filter and a pipe run. Another prices eight machine-side loaders. The third prices a material-room silo, a dryer and a control cabinet, and leaves out the pipe. None of them are wrong; the phrase simply does not contain a project.

What makes the quotes comparable is a numbered map of where material comes from, where it goes, how much of it moves, and how far. That map, plus a plan and elevation drawing and a demand table, is the RFQ. Everything else, including the machine, follows from it.

## Count your sources, then count your receivers

Give every pickup a number: S01, S02, S03. For each, the useful facts are the exact grade, the form (virgin pellet, masterbatch, additive, regrind, flake), the container (bag, gaylord, day hopper, dryer, silo, machine-side granulator discharge), the normal and minimum inventory, and the bulk density. Photograph the outlet and measure the connection. A pickup that works on a 200-liter day hopper may not work on a 1,000 kg gaylord with a different discharge cone.

Do the same for receivers: R01, R02, and so on, whether the receiver sits on a molding machine, an extruder, a hopper dryer, a blender or a day bin. Record the connection size, headroom, support, level signal and the reserve the downstream hopper needs.

Do not lump everything under "plastic pellets." Regrind and flake convey differently from virgin pellets, and a line sized for pellets will plug on flake with a wide particle-size spread. That is a different source with a different number, not a footnote.

## The routing matrix is the whole project on one page

Put sources down the side and receivers across the top, then mark every allowed connection alongside the forbidden ones, because "S02 must never reach R05" is a real requirement when two grades share a plant, and it is the one a supplier will not guess.

The matrix tells you almost immediately what architecture you are buying. If every receiver has exactly one source, you are looking at dedicated machine-side loaders such as our [detachable-receiver vacuum loader](https://kyshinmachinery.com/products/feeding-conveying/detachable-receiver-vacuum-loader). If several sources feed several receivers, you need selection: manual hose stations, automated valves, or a central system with source switching. Each option has a different price and a different cleaning burden, and the matrix is what makes the trade visible.

For manual stations, say how hoses are labeled, how the connection is verified, where hoses are stored and how a line is cleared between materials. For automated selection, say who is allowed to change a route, how position is confirmed, what happens on a wrong route, and what gets recorded.

## Throughput is a peak number, not a daily total

Daily consumption divided by 24 hours is the most common way a conveying system ends up too small. A press that runs a 500 g shot on a 25-second cycle eats 72 kg/h while it is running. Three of them starting up together after a weekend pull 216 kg/h through one blower for the first twenty minutes, and then almost nothing for an hour.

So the demand table needs minimum, normal and peak for each receiver, plus the reserve in each hopper and the longest refill interval you can tolerate. A 50 kg machine hopper at 72 kg/h gives you about 42 minutes of buffer; that is your refill window, and the system has to hit it every time, not on average.

This is where the calculation starts. Suppose one blower serves eight receivers, each needing 72 kg/h at peak (576 kg/h across the group), and the blower loads one receiver at a time in sequence. If each load cycle takes 90 seconds including line purge and valve switching, a full round of eight receivers takes 12 minutes. During those 12 minutes, each press consumes 72 kg/h × (12 ÷ 60) h = 14.4 kg of resin. Every single 90-second load cycle therefore has to deliver at least 14.4 kg into the calling receiver (an instantaneous transfer rate of nearly 580 kg/h during the pull), and the receiver or its downstream throat hopper must hold more than 14.4 kg above its low-level sensor or the machine will starve before its turn comes back around. Whether your hoppers and blower meet both numbers is answerable before anyone quotes.

## Distance, lift and bends are not one number

Send a plan view and an elevation that trace the actual route from each source to each receiver, including horizontal run, vertical lift, high points, downward runs, bend count and location, proposed line diameter, and flexible hose length. Mark walls, ceilings, pipe racks, crane paths, forklift aisles and future machine locations on the same drawing.

A 40 m straight run and a 40 m run with six bends and 8 m of lift are not the same duty. Bends and vertical lift cost pressure, and a vacuum system that is marginal on a clean line will fail once the filter loads. The straight-line distance on a site plan is the least useful number in the RFQ, which is why suppliers who quote from it are the ones who come back for a change order.

## Drying and conveying are two jobs that share a material

State whether each material travels before drying, after drying, or both, and what condition it must be in at the machine. For hygroscopic resin, attach the current supplier data sheet and the target residual moisture.

An enclosed hose is not dry-air conveying. If the process needs dried resin to arrive dry, the RFQ has to describe the air path: where conveying air is drawn, whether it is dried, whether the system is closed-loop, how return air is filtered, and how the conveying arrangement interfaces with the dryer. Our [drying and dehumidifying](https://kyshinmachinery.com/products/drying-dehumidifying) range and our [feeding and conveying](https://kyshinmachinery.com/products/feeding-conveying) range are separate product families for a reason, and the dryer capacity and the conveying capacity have to be sized off the same consumption plan. Where virgin, masterbatch, and regrind also meet along the path, use our [mixing and dosing](https://kyshinmachinery.com/products/mixing-dosing) options to define whether proportioning happens at the throat or in a central blender, and how segregation after mixing is prevented.

## What the package contains, and one thing we cannot do for you

The controlled package is not long: scope and phase boundary; numbered source list with photos; numbered receiver list with photos; the routing matrix; material data sheets; the demand table with peak and startup; dimensioned plan and elevation; drying, dosing and blending requirements; a control narrative with alarms and records; site utilities (voltage, phase, frequency, compressed air, ambient temperature and humidity, noise limits, and safety/guarding rules); cleaning and changeover rules with spares (filters, seals); and the commissioning tests (representative demand, empty-source, blocked-pickup, leaking-line, and wrong-route checks) alongside the quotation format you want back.

We can take that package, lay the route matrix and equipment list against it, and organize a machine- or system-level RFQ across our Zhongshan factory and our manufacturing partners so the bids come back on the same basis. What we cannot do is decide your peak demand or your acceptable refill interval for you. Those come from your cycle times and your production schedule, and a supplier who fills them in with assumptions is writing a quote you will have to renegotiate later.

Start with the matrix. Most RFQs that go wrong were vague at that step, and no amount of detail downstream repairs it. You can send the package through our Contact page, and if the matrix is still half-built, send it anyway — it is easier to finish with the drawings open.

Request a quote

## Send us your material and process details

We will review the application before recommending a machine configuration.

[Request a quote](https://kyshinmachinery.com/contact)

<https://kyshinmachinery.com/guides/material-handling-system-rfq-checklist>